Construction Schedule

Phase 1

  • Reconfigure and rehabilitate the exit ramp from Northbound I-95 to Westbound SR 273. (This ramp will be closed during all of Phase 1.)
  • SR 273 bridge repairs on the Eastbound shoulder behind temporary barrier.
  • Replace high mast lighting.
  • Start curb and guardrail replacement on ramp from Southbound I-95 to Eastbound SR 273 behind temporary barrier. (This ramp will be closed at night (9 p.m. to 6 a.m.) starting March 15 to March 18, 2021, pending weather.)
  • Start curb and guardrail replacement on ramp from Eastbound SR 273 to Northbound I-95 behind temporary barrier.
Detour Information
Interactive Map

Phase 2

  • Rehabilitate the entrance ramp from Westbound SR 273 to Southbound I-95. (This ramp will be closed during all of Phase 2.)
  • Start reconfiguration of the exit ramp from Southbound I-95 to Westbound SR 273.
  • Start Westbound SR 273 pavement widening.
  • Install new Westbound SR 273 traffic signal at Southbound I-95 exit ramp.
  • Complete curb and guardrail replacement on ramp from Southbound I-95 to Eastbound SR 273 behind temporary barrier. (This ramp will be closed for a few consecutive nights (9 p.m. to 6 a.m.) during Phase 2. Dates TBD.)
Detour Information
Interactive Map

Phase 2A

  • All construction described under Phase 2 will continue during this sub-phase.
  • SR 273 bridge repairs on the Westbound outer lanes behind temporary barrier. (Westbound SR 273 will be reduced to one lane during Phase 2A.)
Detour Information
Interactive Map

Phase 3

  • Complete reconfiguration of the exit ramp from Southbound I-95 to Westbound SR 273. (This ramp will be closed for a few consecutive nights (9 p.m. to 6 a.m.) during Phase 3. Dates TBD.)
  • Resurface ramp from Southbound I-95 to Eastbound SR 273. (This ramp will be closed for just a few nights in Phase 3.)
  • Complete Westbound SR 273 pavement widening.
  • Complete bridge repairs on the inside lanes and shoulders of both Eastbound and Westbound SR 273.
  • Install new stormwater management pond.
Detour Information
Interactive Map

Phase 4

  • Rehabilitate the exit ramp from Northbound I-95 to Eastbound SR 273. (This ramp will be closed during all of Phase 4.)
  • Complete curb and guardrail replacement on ramp from Eastbound SR 273 to Northbound I-95 behind temporary barrier.
Detour Information
Interactive Map

Phase 5

Active Phase – May, 2022 (6.5 month estimated duration)
  • Pavement patching and resurfacing of SR 273. (Night-time lane closures and restrictions.)
  • Resurfacing of multiple interchange ramps. (Night-time lane closures and restrictions.)
  • Install overhead sign structures on I-95 and on the exit ramp from Southbound I-95 to Westbound/Eastbound SR273. (Road closures during very restricted night-time hours.)
Detour Information
Interactive Map

Sidebar

Recent Posts

  • Nighttime Lane Restrictions and a Closure on I-95
  • Nighttime Lane Restrictions on I-95 Between Rt.1 and Rt. 273
  • Nighttime Closures of I-95 for Overhead Sign Work
  • Changing Lane Restrictions on Route 273 over I-95
  • Left Lane Closed on WB Rt 273 for Concrete Patching